Construction Material Estimator & BOQ
Project: My Dream Home (Bengaluru)Dashboard

Material Takeoff, Quantities & Stage-wise BOQ

Detailed material requirements calculated using civil engineering standards (IS codes) adjusted for Bengaluru and Premium grade construction.

Estimated Budget
₹55,96,740
Built-up Area: ~1860 sqft @ ₹3009/sqft
Material Subtotal
₹17,79,553
Civil + finishing raw material takeoff
Estimated Timeline
~9 Months
Excavation to final handover

Comprehensive Material Schedule

Premium Specification
Material CategoryRequired QuantityApprox RateTotal Est. Cost
Cement (OPC 53 / PPC)For RCC casting, masonry mortars and wall plaster781 Bags (50 kg)390 / Bags₹3,04,590
TMT Steel Rebars (Fe 550D)Columns, footings, plinth beams, lintels and slab reinforcement7.1 Metric Tonnes68,000 / Metric₹4,80,624
Red Clay / AAC BlocksExternal 9" walls and internal 4.5" partition walls33,480 Pieces / Blocks9.5 / Pieces₹3,18,060
Manufactured Sand (M-Sand & P-Sand)Graded fine aggregate for concrete mixes and wall plastering3,348 Cubic Feet (cu ft)62 / Cubic₹2,07,576
Coarse Aggregate (20mm & 10mm)Hard crushed stone for concrete grade M20/M252,511 Cubic Feet (cu ft)48 / Cubic₹1,20,528
Vitrified Tiles & Stone DADOLiving, bedroom double-charged vitrified tiles + bathroom anti-skid2,325 Square Feet (sq ft)95 / Square₹2,20,875
Putty, Primer & Emulsion PaintsInterior acrylic emulsion + weatherproof exterior silicone paint335 Litres380 / Litres₹1,27,300

Material Cost Share

Major Construction Stage Allocation (₹ Thousands)